July 25, 2024
Notice: Completion of Environmental Site Assessment & Remediation Work

(PDF)

June 24, 2024
Notice: Environmental Site Assessment & Remediation Work

(PDF)

June 10, 2024
Notice: Transmission Line Work

(PDF)

April 30, 2024
Notice: Westwood Partner Conducting Geotech & Pile Load Fieldwork

(PDF)

April 10, 2024
Notice: Westwood Ground Survey & Topography Surface Mapping

(PDF)

March 25, 2024
Notice: ESA Work & EPC Walk

(PDF)

March 5, 2024
Press Release: Arevon and Meta Announce Long-Term Contracts for 349 Megawatts of New Solar Energy

(PDF)

October 20, 2023
Notice: Westwood in the Area

(PDF)

October 17, 2023
Notice: Construction Activity

(PDF)

September 20, 2023
Notice: Field Surveys

(PDF)

July 5, 2023
2023 Switchyard Construction Activity

(PDF)

May 19, 2023
Upcoming Field-Testing Information

(PDF)

Media Inquiries

For reporter questions, please contact Trish Evans at tevans@arevonenergy.com or (405) 513-3472.  For other matters, please visit our contact page.

Information Resources

Sign up to receive Kelso Solar project updates via email.

Your information is collected for communication purposes only and will not be shared with any third parties. For more details on what we do with your information, please read our privacy policy.

bottom of page